  4.  | NANA Construction Plans Major Expansion of Fabrication Facility in Mat-Su

NANA Construction Plans Major Expansion of Fabrication Facility in Mat-Su

Jun 27, 2019 | Monitor

Aerial view of NANA Construction’s Big Lake facility as it currently stands.

NANA

BIG LAKE—One of Alaska’s largest fabrication facilities will soon double its current industrial fabrication capacity. NANA Construction plans to expand its Big Lake facility this summer, increasing its existing industrial fabrication space from 14,000 square feet to 28,000 square feet—making it the largest facility of its kind in the state.

NANA Construction began seeing a growing demand for process module fabrication and constructability support late last year, and given the project forecast for the coming months, NANA leadership approved the expansion to meet increasing client needs.

“We’re a customer-driven company,” said John Hendrix, president of NANA’s Commercial Group. “We don’t ever want to turn down a project because we lack the capacity or space to do it. With this expansion, we’re taking proactive steps in recognition of the work ahead.”

Preliminary plans include the addition of a 240-foot by 60-foot, pre-engineered metal building featuring two, 10-ton overhead cranes, bringing the total number of industrial cranes at the facility to eighteen. NANA Construction’s fabrication facility sits on more than thirty-two acres of cleared, fenced land at mile 2.1 Big Lake Road, just north of Wasilla. Its strategic location significantly reduces travel time for the truckable, industrial modules that are manufactured there and destined for the North Slope. The site comprises multiple buildings, including one acre of covered, interior floor space; a prep and coat shop and segregated Class 1 paint shop; and an industrial fabrication and assembly shop. When combined with the site’s commercial capacity, the industrial fabrication expansion will increase the facility’s total space to 102,000 square feet.

NANA Construction views the expansion as an asset not only to North Slope and Red Dog Mine operations, but also to Alaska’s economy.
“More space means more capacity for work, which means more jobs,” said General Manager Fred Elvsaas. “We’ll be able to accommodate more units inside the facility, allowing for longer-term projects and increased production.”

NANA Construction expects to complete the expansion by fall 2019.

Piping fabrication and installation on the Brooks Range LACT module. The module will ship in July to be installed at the Mustang Pad on the North Slope.

NANA

Current Issue

Alaska Business May 2024 Cover

May 2024

Industry Sponsor

Become an Industry Sponsor

Alaska Business May 2024 cover
In This Issue

Making History

May 2024

The track of oil and gas development in Alaska shows the footprints of bold companies and hard-working individuals who shaped the industry in the past and continue to innovate today. The May 2024 issue of Alaska Business explores that history while looking forward to new product development, the energy transition for the fishing fleet, and the ethics of AI tools in business.

Share This