State Proposes rehabilitation of the Tok Cutoff between mile posts 38 and 50


Published:

Heaves in the Tok Cutoff between mile posts 38 and 50.

Courtesy photo

The Alaska Department of Transportation and Public Facilities (ADOT&PF), in cooperation with the Alaska Division of the Federal Highway Administration, is proposing to rehabilitate the Tok Cutoff between mile posts 38 and 50. Improvements will include drainage, embankment stabilization and rebuilding pavement structure. The project also includes railing upgrades and deck repairs to the Indian River Bridge #651.

The purpose of this project is to improve safety and mobility for all users, and to reduce maintenance requirements along the project corridor. It is needed because the road experiences excessive frost heaving and settlement due to subgrade failure and drainage problems.

The Department plans to use the Construction Manager/General Contractor (CMGC) project delivery method to assist in the development of the design incorporating innovative materials and methods, and to construct the project in a manner that minimizes impacts, reduces risks, and provides cost savings through efficient scheduling and utilization of construction materials.

Contractors are invited to attend a meeting on Monday, November 13, 2017 from 1:30 pm to 3:30 pm to learn more about the contractor selection process, CMGC and the Tok Cutoff MP 38-50 Rehabilitation project. Contractors may join in person at the locations identified below or via the web at the WebEx link listed below. Please register if you plan to attend by sending an email to Contracts Engineer, Barbara Tanner barbara.tanner@alaska.gov. with the subject heading TOK CUTOFF CMGC RSVP

Access Information:

Meeting Number: 994 574 153

Meeting Password: This meeting does not require a password.

Audio Connection: 571-209-6390 (Cisco WebEx)

Access Code: 994 574 153 

 

If you have questions or require clarification, please contact the project manager or visit the project web site. The proposal documents can be viewed and downloaded from the procurement website.

Russell Johnson, P.E., ADOT&PF Project Manager

Tel: 907-451-5059, Fax: 907-451-5126, TDD: 907-451-2363, E-mail: Russell.Johnson@alaska.gov


DOT&PF operates Federal Programs without regard to race, color, national origin, sex, age, or disability. Full Title VI Nondiscrimination Policy: http://dot.alaska.gov/tvi_statement.shtml. To file a complaint, go to: http://dot.alaska.gov/cvlrts/titlevi.shtml. DOT&PF complies with Title II of the Americans with Disabilities Act of 1990. Individuals with disabilities who may need auxiliary aids, services, and/or special modifications to participate in this outreach meeting should contact the project manager listed above. Requests should be made at least 10 days before the accommodation is needed to make any necessary arrangements. To correspond by text telephone (TDD), call (907) 451-2363.

Edit Module

Add your comment:
Edit Module Edit ModuleShow Tags
Edit ModuleShow Tags
Edit ModuleShow Tags
Edit ModuleShow Tags
Edit ModuleShow Tags
Edit ModuleShow Tags

Connect With Us

   

 

Edit ModuleShow Tags

Most Read