Anchorage Road Projects Traffic Delays

Anchorage Roads

Road Project Traffic Delays Last Updated October 6, 2011

1. Huffman Road between Old Seward Hwy. and New Seward Hwy. The Huffman Rd./New Seward Hwy. roundabout are now open. Please be alert to new traffic patterns. Visit http://www.alaskaroundabouts.com/ for driving tips.

Drivers should expect daily lane restrictions on Huffman Rd. from Pintail St. to Gregory Rd. between 7:30 AM and 5:00 PM.

Be alert to paving operations on the pedestrian pathway, from Pintail St. to Gregory Rd. between 8:00 AM and 6:00 PM.

Expected Completion: October, 2011

Information: DOT, 269-0450 or here for more information.

2. 72nd Ave. btwn. Lake Otis Pkwy. and Brayton Dr. Drivers should expect intermittent lane closures and flagging operations on 72nd Ave. between Lake Otis Pkwy. and Brayton Dr. for road improvements. Please use caution in the area.

Expected Completion: October, 2011

Information: AIC, 562-2792

3. E. 40th Ave. btwn. Lake Otis Pkwy. and Piper St. The Piper St. roundabout is now open. Please be alert to new traffic patterns.

Dale St. is closed at E. 41st Ave. until October. Please use alternate routes.

Drivers should expect intermittent lane restrictions and flagging operations on E. 40th Ave. between Lake Otis Pkwy. and Piper St. for major road improvements. Drivers should also expect intermittent lane restrictions on Lake Otis Pkwy. at W. 40th Ave. between 9:00 AM and 4:00 PM.

Expected Completion: October, 2011

Information: Pruhs Construction, 444-3560

4. Glenn Hwy. btwn. South Birchwood and Eklutna Drivers should expect shoulder restrictions and intermittent lane restrictions, Monday through Saturday, on the southbound Glenn Hwy. between 9:00 AM and 8:00 PM, and on the northbound Glenn Hwy. between 5:30 AM and 4:00 PM.

Expected Completion: October, 2011

Information: DOT, 622-4111; Elcon Inc., 688-8510

5. Independence Dr. btwn. Jamestown and O'Malley Rd. Drivers should expect an intermittent road closure on Independence Dr. between Jamestown and O'Malley Rd. for road improvements. Residents will maintain alternate access. Please follow detour routes.

Expected Completion: End of season, 2011

Information: Roger Hickel Contracting, 279-1400

6. Fairbanks St. btwn. W. 7th Ave. and W. 9th Ave. Drivers should expect a full closure on Fairbanks St. between W. 7th Ave. and W. 9th Ave. for utility work. Please use detour routes.

Expected Completion: Tuesday, October 11

Information: Municipal Light & Power, 263-5283

7. E St. btwn. W. 4th Ave. and W. 5th Ave. On Sunday, October 9th between 9:00 AM and 4:00 PM, drivers should expect a full road closure on E St. between W. 4th Ave. and W. 5th Ave. for construction equipment setup. Please use alternate routes.

Information: Zelner Group, 278-7236
 