Anchorage Roads - May 20

Road Project Traffic Delays Last Updated May 20, 2010

Thank you for visiting Anchorageroads.org.  Please expect road construction at the following locations:

1) Lake Otis Pkwy. and Tudor Rd. Intersection The intersection of Lake Otis Pkwy. and Tudor Rd. will be closed from Friday, May 21st at 8:00 PM through Monday, May 24th at 6:00 AM. Business access will be permitted during these closures. Please follow construction signs for detour routes.

Lake Otis and Tudor Plaza access will be permitted from the Lake Otis entrance and Tudor entrance. Access to the Tudor Medical Plaza and the Frontier Mall will be permitted from Laurel Street via Tudor.

Drivers should expect new traffic patterns and multiple lane closures through July. Drivers should also expect flagging operations near and at the intersection of Lake Otis Pkwy. and Tudor Rd. for major road reconstruction. Nighttime construction activity is actively taking place.  Please drive with caution and obey all traffic control devices and reduced speed limits.

Expected Completion: October, 2010

Information: QAP, 522-2211; DOT, 646-2300 or click here for more information.

2) Old Seward Hwy. between O'Malley Rd. and Brandon St. The Old Seward Hwy. will be closed at 120th Ave. from Saturday, May 22nd at 6:00 AM through Monday, May 24th at 6:00 AM.

Beginning Monday, May 24th, drivers should expect one-lane traffic and detour routes at Brandon St. and Cross St.

Drivers should be alert to intermittent lane restrictions and delays through August. Please watch for construction crews, follow appropriate detour routes and drive safely.

Expected Completion: August, 2010

Information: QAP, 770-0803; DOT, 868-3615

3) Spenard Rd. north of Hillcrest Dr. Drivers should expect a full road closure on Spenard Rd. north of Hillcrest Dr. for road and pedestrian improvements. Only local residential access to 19th Ave. and Hillcrest Dr. will be maintained. Please follow appropriate detour routes and construction signs.

Expected Completion: July, 2010

Information: CUI, 243-8667

4) W. 5th Ave. at B St. Beginning Friday, May 21st at 8:00 PM through Monday, May 24th at 6:00 AM, the intersection of W. 5th Ave. and B St. will be closed to traffic. Please follow construction signs for detour routes.

Information: Granite Construction, 344-2593 or click here or more information.

5) W. 9th Ave. between I St. and L St. Drivers should expect  a full road closure on W. 9th Ave. between I St. and L St. for road and pedestrian improvements. The intersections of I St. and  L St. will remain open. Please follow appropriate detour routes and construction signs. This section of W. 9th Ave. is expected to be closed for several weeks.

FUTURE CLOSURE: Beginning Friday, May 28th at 8:00 PM through Tuesday, June 1st at 6:00 AM, drivers should expect a full road closure at the intersection of W. 9th Ave. and L St. for road and pedestrian improvements. Please follow appropriate detour routes and construction signs.

Expected Completion: Project Completion, October, 2010

Information: CUI, 243-8667

6) Muldoon Rd. between E. 36th Ave. and Glenn Hwy. Drivers should expect lane restrictions and delays at the intersection of Muldoon Rd. and E. 6th Ave. for road construction. Please use alternate routes to avoid delays.

Expected Completion: Mid-August, 2010

Information: Pruhs Construction, 350-6908; DOT, 332-3145

7) E St. between 4th Ave. and 5th Ave. Beginning Thursday, May 20th, drivers should expect a single northbound lane closure on E St. between 4th Ave. and 5th Ave. for Egan Center roof repair equipment staging. Please use caution when driving through the area.

Expected Completion: Sunday, June 20th

Information: Earhart Roofing. 345-5555

8) Chester Creek Trail Improvements The Northern Lights trail, from Wesleyan Dr. to Goose Lake Park is closed until Saturday, June 19th. When the trail reopens it will be gravel until the trail is paved in August. Pedestrians will be detoured to cross to the northern sidewalk of Northern Lights at the UAA Dr. and Northern Lights intersection, and at the east pedestrian overpass (east of Bragaw) or Wesleyan and Northern Lights intersection, depending on construction activities.

The pedestrian overpass will be closed weekdays from 8:00 AM to 5:00 PM. It will be open until 9:00 AM on Friday, May 21st.

Information: Roger Hickel Construction, 336-4133, DOT, 269-8756 or click here for more information.

9) Old Glenn Hwy. from West Lake Ridge Dr. to S. Birchwood Loop Rd. The Old Glenn Hwy. from West Lake Ridge Dr. to Fish Hatchery Rd. will be closed for approx. 6 weeks starting on Friday, May 21st at 7:00 AM until Thrusday, July 1st at 6:00 AM for road construction. Please follow construction signs for detour routes.

At other times, be alert to lane restrictions and flaggers.

Expected Completion: October, 2010

Information: Pruhs Construction

10) Glenn Hwy. Resurfacing - Hiland Rd. to Eklutna Rd. Drivers should expect nightly lane restrictions, reduced speed limits and intermittent ramp closures at the South Eagle River interchange through Friday, May 21st between 9:00 PM and 5:00 AM. Please follow construction signs for detour routes.

Information: QAP, 522-2211; DOT, 622-5111

11) 36th Ave. between Denali St. and Old Seward Hwy. FUTURE CLOSURE: Beginning Friday, May 28th at 8:00 PM through Wednesday, June 2nd at 6:00 AM, drivers should expect a full road closure on 36th Ave. between Denali St. and Old Seward Hwy. for road and utility work. Please follow appropriate detour routes.

Information: BC Excavating, 344-4490

12) Mountain View Dr. between Park St. and Hoyt St. Beginning Friday, May 21st at 6:00 PM through Tuesday, May 25th at 6:00 AM, drivers should expect a full road closure on Mountain View Dr. between Park St. and Hoyt St. for road and utility work. Please follow appropriate detour routes.

Information: BC Excavating, 344-4490

13) Elmore Rd. at O'Malley Rd. Beginning Friday, May 21st at 8:00 PM through Monday, May 24th at 6:00 AM, drivers should expect a full road closure at the intersection of Elmore Rd. and O'Malley Rd. for major waterline installation. Local and emergency vehicle access wil be maintained at all times.

Information: GMC Contracting, 561-4733

14) Anchorage Market and Festival - W. 3rd Ave. between C St. and E St. Drivers should expect lane closures and short delays on W. 3rd Ave. between C St. and E St. for the Anchorage Market and Festival through Sunday, September 5th (Saturdays and Sundays only). Please watch for pedestrians and drive with caution.

Information: Webb's Consulting, 272-5635

15) Arctic Blvd. between International Airport Rd. and Tudor Rd. Drivers should expect intermittent single right lane closures on Arctic Blvd. between International Airport Rd. and Tudor Rd. weekdays between 9:00 AM and 4:00 PM for road improvements.

Expected Completion: June, 2010

Information: Alaska Frontier Services, 345-8954

16) Dimond Blvd. at Jewel Lake Rd. Beginning Thursday, May 20th, drivers should expect intermittent lane restrictions at thte intersection of Dimond Blvd. and Jewel Lake Rd. for road improvements.

Expected Completion: August, 2010

Information: Granite Construction, 344-2593; DOT, 646-9617

17) Minnesota Dr. between Raspberry Rd. and Dimond Blvd. Drivers should expect nightly lane restrictions on Minnesota Dr. between Raspberry Rd and Dimond Blvd. for weigh station and pavement upgrades.

Expected Completion: July, 2010

Information: DOT, 646-9640

18) Brayton Dr./Frontage Rd. Drivers should expect shoulder work on Brayton Dr./Frontage Rd. and future lane closures for clearing work. Upon completion, the Frontage Rd.will be aligned with Brayton Dr.and transition from the Frontage Rd. to the New Seward Hwy. will be smoother.

Expected Completion: September, 2010

Information: Granite Construction, 344-2593; DOT, 646-9617

19) Debarr Rd. at Edward St. Drivers should expect nightly lane restrictions between 8:00 PM and 6:00 AM at the intersection of Debarr Rd. and Edward St. for road improvements.

Expected Completion: July, 2010

Information: Granite Construction, 344-2593; DOT, 646-9617

20) Bridge Inspection of Anchorage Port Access Beginning Wednesday, May 19th, drivers should expect lane restrictions on 1st Ave. between C St. and Cordova St. Please use caution when travelling through the area.

Expected Completion: May, 2010

Information: DOT, 209-1899

21) Hilltop Dr. between Klatt Rd. and Old Klatt Rd. Drivers should expect a full road closure on Hilltop Dr. between Klatt Rd. and Old Klatt Rd. for utility work. Please follow appropriate detour routes.

Expected Completion: Wednesday, June 2nd

Information: John's Excavating, 563-1635

22) E. 1st Ave. between A St. and Cordova St. Beginning Tuesday, May 25th, drivers should expect an intermittent road closure on E. 1st Ave. between A St. and Cordova St. Please follow appropriate detour routes.

Expected Completion: Wednesday, June 8th

Information: Loundsbury & Associates, 272-5451

23) Providence Dr. between Laurel St. and Piper St. FUTURE CLOSURE: Beginning Friday, May 28th at 8:00 PM through Wednesday, June 2nd at 6:00 AM, drivers should expect a full eastbound road closure on Providence Dr. between Laurel St. and Piper St. for road and utility work. Westbound traffic will be reduced to one lane. Please follow appropriate detour routes.

Information: Renegade Equipment, 346-2300

24) Old Glenn Hwy. between S. Birchwood Lp. Rd. and Peter's Creek PUBLIC OPEN HOUSE: DOT and Granite Construction will be hosting a public open house on Friday, May 21st at 7:00 PM to 9:00 PM at the Chugiak Fire Dept. Project teams will be available to discuss the schedule and phasing stages of the project.

Expect lane restrictions and flagging operatios on the Old Glenn Hwy. from the Ski Rd. intersection to the Peter's Creek Bridge.

Information: Granite Construction, 344-2593; DOT, 694-6441

25) Boniface Pkwy. at Mountain View Dr. Drivers should expect heavy equipment and construction workers on the roadway and shoulder for road construction.

Expected Completion: July, 2010

Information: Granite Construction, 344-2593; DOT, 646-9617