|  August 1, 2014  |  
Mostly Cloudy   57.0F  |  Forecast »
Bookmark and Share Email this page Email Print this page Print Feed Feed

Road Project Traffic Delays: July 10, 2014

Last Updated: July 10, 2014

1. Arctic Blvd. btwn. W. Potter Dr. and Raspberry Rd.

Arctic Blvd. is CLOSED from W. Potter Dr. to Raspberry Rd. until approx. the end of August. Business access will be maintained. Please follow construction signs for detour routes. International Airport Rd. to Electron Dr. will be open as detour access to Napa and Alaska Steel.

Please use caution and be alert to flagging operations when traveling through the project area.

Expected Completion: October, 2015

Information: Granite Construction, 267-5283; DOT, 929-7244

2. G St. btwn. W. 4th Ave. and W. 5th Ave.

Beginning Sunday, July 13th at 6:00 AM through Saturday, July 20th at 6:00 PM, G St. will be CLOSED between W. 4th Ave. and W. 5th Ave. for utility work. Sidewalks will remain open for pedestrian traffic. Please use detour routes.

Information: Criterion General, 277-3200

3. W. 4th Ave. btwn. B St. and Barrow St.

Beginning Friday, July 11th at 8:00 PM through Monday, July 14th at 6:00 AM, drivers should expect a full road closure on W. 4th Ave. between A St. and B St. and on Barrow St. between W. 4th Ave. and W. 3rd Ave. for road improvements. Please use detour routes.

Information: GMG General, 349-7854

4. McRae Rd. btwn. Barbara Dr. and Wisconsin St.

Drivers should expect intermittent closures on McRae Rd. between Barbara Dr. and Wisconsin St. for road improvements. Please use detour routes.

Expected Completion: July, 2014

Information: Pruhs Construction, 441-7555

5. Bear Paw Festival (Eagle River area)

Drivers should expect multiple road closures beginning Friday, July 11th through Sunday, July 13th for the Bear Paw Festival in Eagle River. The following roads will be impacted:

  • Business Blvd. at Regency Dr. will be CLOSED from Friday, July 11th at 10:00 AM until Sunday, July 13th at 5:00 PM
  • Old Glenn Hwy., Business Blvd., Centerfield Dr., Monte Rd. and Old Eagle River Rd. will be closed and have limited access on Saturday, July 12th from approx. 6:00 AM until approx. 3:00 PM. Please use alternate routes.

APD officers will assist with traffic control. Please obey traffic control devices and use caution in the area.

Information: Chugiak-Eagle River Chamber of Commerce, 694-4702

6. K St. btwn. W. 3rd Ave. and W. 4th Ave.

Drivers should expect a northbound lane closure on K St. between W. 3rd Ave. and W. 4th Ave. from 7 AM - 6 PM. From 6 PM - 7 AM, drivers should expect an intermittent full road closure of this block. Please use detour routes.

Expected Completion: Sunday, July 27th

Information: Cornerstone General Contractors, 561-1993

7. A St. btwn. Northern Lights Blvd. and W. 9th Ave.

FUTURE ROAD CLOSURE: A St. is anticipated to be CLOSED in mid or late July from Fireweed Ln. to 9th Ave. Please follow construction signs for detour routes.

Be alert to new traffic patterns on A St. between Northern Lights Blvd. and 9th Ave., where lanes have been shifted to the west.

Please use caution when traveling through the work zone and be alert to construction workers and heavy equipment on the roadway and shoulder.

Expected Completion: End of Season

Information: DOT, 770-2612

8. W. 71st Ave. Sewer Rehab Project

Drivers should expect intermittent closures on the following roads for the W. 71st Ave. sewer rehab project:

  • Stanley Dr. between W. 71st Ave. and W. 72nd Ave.
  • Rovenna Ln. between W. 71st Ave. and W. 72nd Ave.

Residents will maintain limited acess. Please use detour routes.

Expected Completion: July, 2014

Information: Construction Unlimited, 243-8667

9. Eagle River Rd. Rehabilitation (Upper Terrace Dr. to Eagle River Nature Center)

Drivers should expect lane restrictions, flagging and pilot car operations, and short delays from approx. 8:30 AM to 9:30 PM Monday through Saturday, between Upper Terrace Street (MP 5.3) and Berryhill Road (MP 6.4), and between Eklund Avenue (MP 10.2) and Mount Yukla Circle (MP 12.6). At all other times, be alert to intermittent reduced speed limits, flagging operations, and lane restrictions throughout the project area.

Be alert to construction workers on shoulder and expect delays during hours of construction.

Expected Completion: End of Season

Information: Pruhs, 279-1020; DOT, 622-5111, or email eagleriverroad@spawnak.com

10. Pioneer Dr. btwn. Muldoon Rd. and Resurrection Dr.

Drivers should expect intermittent lane closures on Pioneer Dr. between Muldoon Rd. and Resurrection Dr. for road improvements. Please use caution and follow traffic control devices.

Expected Completion: August, 2014

Information: Prosser-Dagg, 830-8466

11. W. Northern Lights Blvd. at Forest Park Dr.

Drivers should expect intermittent lane restrictions and flagging operations on W. Northern Lights Blvd. at Forest Park Dr. between 8:30 AM and 4:00 PM daily for pedestrian improvements. Please use caution in the area.

Expected Completion: July, 2014

Information: Anchor, Inc., 230-2743

12. Northern Lights Blvd. at UAA Dr.

Be alert to lane restrictions on Northern Lights Blvd. at UAA Drive on Saturdays and Sundays, from 7:00 AM to 5:00 PM.

Please watch for construction workers on the shoulder, and use caution when traveling through the construction area.

Expected Completion: October. 2014

Information: Anchor, Inc., 230-2743; DOT, 770-2612

13. Debarr Rd. Resurfacing (Muldoon Rd. to Airport Heights Dr.)

Use caution when driving through the construction area, and be alert to workers on the roadway and shoulder.

Expected Completion: October, 2014

Information: QAP, 222-3742

14. Anchorage Market & Festival

Drivers should expect lane restrictions and increased pedestrian traffic on Saturdays and Sundays from 6:00 AM - 6:00 PM on 3rd Ave. between C St. and E St. for the Anchorage Market & Festival. Please use caution in the area.

Expected Completion: Sunday, Sept. 7th

15. Resurrection Dr. at Pioneer Dr.

Drivers should expect intermittent closures on Resurrection Dr. at Pioneer Dr. for road and utility improvements.. This closure will be in phases and will move along Resurrection Drive. Please use signed detour routes for residential access.

Expected Completion: August, 2014

Information: Roger Hickel Contracting, 748-0634

16. Penland Pkwy. btwn. Airport Heights and Northway Dr.

Drivers should expect a full road closure on Penland Pkwy. between Airport Heights and Northway Dr. for road improvements. Please use detour routes. Mall access will be provided.

Expected Completion: July, 2014

Information: Mass-X, 771-9272

17. 15th Ave. btwn. Gambell St. and Lake Otis Pkwy.

Drivers should expect intermittent lane restrictions and short delays on 15th Ave. between Gambell St. and Lake Otis Pkwy. for road improvements. Please use caution in the area.

Expected Completion: September, 2014

Information: Roger Hickel Contracting, 903-1703

18. W. 32nd Ave. Sewer Upgrade

Drivers should expect intermittent road closures at the following locations for sewer upgrade work:

  • W. 29th Ave. at Doris
  • W. 32nd Ave. at Lois Dr.
  • W. 32nd Ave. at Willow St.

Please use detour routes. Residential access will be provided at all times unless prior notice is given.

Expected Completion: July, 2014

Information: Construction Unlimited, 441-0303

19. E. 20th Ave. btwn. Sitka St. and Lake Otis Pkwy.

Drivers should expect intermittent full road closures on E. 20th Ave. between Sitka St. and Lake Otis Pkwy. for road improvements. Please use detour routes for residential access.

Expected Completion: End of season

Information: Pruhs Construction, 441-7555

20. E. 22nd Ave. btwn. Illian Ln. and Wayne St.

Drivers should expect a full road closure on E. 22nd Ave. between Illian Ln. and Wayne St. for water utility work. Please use detour routes.

Expected Completion: August, 2014

Information: Annette's Trucking, 344-9322

21. New Seward Hwy. btwn. Dowling Rd. and Tudor Rd.

Be alert to new traffic patterns on the New Seward Hwy. and both frontage roads from Dowling Rd. to Tudor Rd.

Expect intermittent lane restrictions on Homer Dr. and Brayton Dr. due to striping operations and be cautious of wet paint.

Expected Completion: End of season

Information: QAP, 222-3742

22. Eagle River Ln. btwn. Highland Ridge Dr. and Ptarmigan Blvd.

Drivers should expect a full road closure on Eagle River Lane between Highland Ridge Dr. and Ptarmigan Blvd. for road improvements. Please use alternate routes.

Expected Completion, August, 2014

Information: Mass-X, 771-9272

23. Wendy's Way btwn. W. Northern Lights Blvd. and Bridle Ln.

Beginning approx. June 1st, drivers should expect intermittent full road closures on Wendy's Way between W. Northern Lights Blvd. and Bridle Ln. for sewer utility work. Please use detour routes. Residents will maintain access.

Expected Completion: August, 2014

Information: BC Excavating, 344-4490

24. Kachemak Pl. at Kachemak Circle

Drivers should expect intermittent closures on Kachemak Circle and Kachemak Pl., and on Amber Bay Loop at Kachemak Pl. for road and utility work. Please use detour routes. Residential access will be maintained.

Expected Completion: July, 2014

Information: Renegade Equipment, 346-2300

25. W. 10th Ave. btwn. S St. and R St.

Drivers should expect intermittent closures on W. 10th Ave. between S St. and R St. for work. Please use detour routers.

Expected Completion: Monday, July 7th

Information: GLW Enterprises, 250-5036

26. Sycamore Lp. btwn. E. 36th Ave. and Pioneer Dr.

Drivers should expect an intermittent road closure on Sycamore Loop between E. 36th Ave. and Pioneer Dr. for water utility work. Please use detour routes.

Expected Completion: Tuesday, July 8th

Information: AWWU, 564-2700

27. San Roberto Ave. btwn. Klevin St. and Hoyt St.

FUTURE CLOSURE: Beginning Monday, July 14th, drivers should expect an intermittent road closure on San Roberto Ave. between Klevin St. and Hoyt St. for road work, 7:00 AM to 7:00 PM, daily. Please use detour routes.

Expected Completion: September, 2014

Information: AWWU, 564-2700

28. Klevin St. btwn. Debarr Rd. and E. 16th Ave.

Beginning Monday, July 21st, drivers should expect a full road closure on Klevin St, between Debarr Rd. and E. 16th Ave. for utility work. Please use detour routes.

Expected Completion: Thursday, July 24th

Information: AWWU, 564-2700

29. Maplewood St. btwn. E. 24th Ave. and Bannister Rd.

Drivers should expect an intermittent full road closure on Maplewood St. between E. 24th Ave. and Bannister Rd. for sewer service. Please use detour routes. Residents will maintain access unless given prior notice.

Expected Completion: Monday, July 7th

Information: Sanders and Sanders, 223-1887

30. Richmond Ave. btwn. Price St. and Bragaw St.

Drivers should expect an intermittent full road closure on Richmond Ave. between Price St. and Bragaw St. for work. Please use detour routes.

Expected Completion: Monday, July 7th

Information: Davis Construction, 562-2336

31. Bunn St. btwn. Mountain View Dr. and Peterkin St.

Drivers should expect an intermittent full road closure on Bunn St. between Mountain View Dr. and Peterkin St. for work. Please use detour routes.

Expected Completion: Friday, July 18th

Information: Davis Construction, 562-2336

32. W. 7th Ave. btwn. H St. and I St.

FUTURE CLOSURE: Beginning Monday, July 14th, drivers should expect a full road closure on W. 7th Ave. between H St. and I St. for utility work. Please use detour routes.

Expected Completion: Thursday, July 17th

Information: AWWU, 564-2700

33. Glade Pl. btwn. E. 73rd Ave. and E. 74th Ave.

Drivers should expect an intermittent full road closure on Glade Pl. between E. 73rd Ave. and E. 74th Ave. for site work. Residential access will be arranged. Please use detour routes.

Expected Completion: Friday, July 11th

Information: Amaq Excavating, 529-7222

34. Porcupine Dr. at Rampart Dr.

Drivers should expect an intermittent flagging operation and short delays at the intersection of Porcupine Dr. at Rampart Dr. from 9:00 AM - 4:00 PM daily.

Expected Completion: Tuesday, July 15th

Information: BGES, 748-9955

35. Senate District J (Muldoon Area Repaving)

Drivers should expect intermittent closures at the following areas for road improvments:

  • Augustine Dr. between E. Northern Lights Blvd. and Lake George Dr.
  • Brittany Dr. between Scarborough Dr. and E. Northern Lights Blvd.
  • Patterson St. between E. Northern Lights Blvd. and Chandalar Dr.

Residential access will be maintained. Please use signed detour routes.

Expected Completion: July, 2014

Information: GMG, 349-7854

36. Post Rd. at E. 1st Ave.

Beginning Thursday, July 10th, drivers should expect a full road closure at the intersection of Post Rd. and E. 1st Ave. for railroad improvements. Please use detour routes.

Expected Completion: Sunday, July 13th

Information: Alaska Railroad, 265-2237

37. Latouche St. btwn. E. 15th Ave. and E. 16th Ave.

Drivers should expect an intermittent closure on Latouche St. btwn. E. 15th Ave. and E. 16th Ave. for site work. Please use detour routes.

Expected Completion: Monday, July 21st

Information: Harrison Quality Homes, 884-1041

38. Tudor Centre Dr. at Diplomacy Dr.

Drivers should expect a northbound lane closure on Tudor Centre Dr. at Diplomacy Dr. for site work. Please use detour routes.

Expected Completion: Thursday, July 10th

Information: PCL Construction, 243-7252

39. Petersburg St. btwn. Dimond Hook Dr. and E. 79th Ave.

Drivers should expect an intermittent closure on Petersburg St. between Dimond Hook Dr. and E. 79th Ave. for water utility work. Please use detour routes.

Expected Completion: Monday, July 14th

Information: AWWU, 564-2700

40. Grand Larry St. btwn. Boundary Ave. and Peck Ave

Beginning Wednesday, July 16th, drivers should expect an intermittent road closure on Grand Larry St. between Boundary Ave. and Peck Ave. for utility work. Please use detour routes.

Expected Completion: Monday, July 28th

Information: Beek's Contracting, 306-1352

41. Northwood Dr. at W. 88th Ave.

Drivers should expect an intermittent flagging operation on Northwood Dr. at W. 88th Ave. from 9:00 AM to 4:00 PM for guardrail repair. Please use caution in the area.

Expected Completion: Wednesday, July 23rd

Information: Acme Fence, 240-9227

42. W. 32nd Ave. btwn. A St. and C St.

Beginning Monday, July 14th through Thursday, July 17th, from 7:00 AM - 4:00 PM daily, drivers should expect a full road closure on W. 32nd Ave. between A St. and C St. for road repairs. Please use detour routes.

Information: Municipal Street Maintenance, 343-8182

43. W. 48th Ave. btwn. Van Buren St. and Northwood Dr.

Drivers should expect an intermittent closure on W. 48th Ave. between Northwood Dr. and Van Buren St. for gas utility work. Please use detour routes. Residents will maintain access.

Expected Completion: Friday, July 25th

Information: Enstar, 240-8654

44. W. 32nd Ave. btwn. Wisconsin St. and Turnagain St.

Beginning Monday, July 14th, drivers should expect a full road closure on W. 32nd Ave. between Wisconsin St. and Turnagain St. from 7:00 AM to 4:00 PM, daily. Please use detour routes.

Expected Completion: Friday, July 18th

Information: Municipal Street Maintenance, 343-8182

45. E. 40th Ave. btwn. Old Seward Hwy. and Denali St.

Drivers should expect lane restrictions on E. 40th Ave. between Old Seward Hwy. and Denali St. for storm drain repair. Please use caution in the area.

Expected Completion: Tuesday, July 22

Information: Neeser Construction, 276-1058

46. W. 25th Ave. at Spenard Rd.

On Saturday, July 12th from 9:00 AM - midnight, drivers should expect a full road closure on W. 25th Ave. east of Spenard Rd. for a Chilkoot Charlie's event. Please use alternate routes.

Information: Chilkoot Charlie's, 223-7817

47. W. 10th Ave. btwn. G St. and I St.

On Saturday, July 12th from 7:00 AM until 4:00 PM, drivers should expect a full road closure on W. 10th Ave. between G St. and I St. for the Governor's Family Picnic. Please use alternate routes.

Information: Governor's Family Picnic Committee, 269-3034

Add your comment:
Advertisement
Advertisement
Advertisement
Advertisement
Advertisement